Transcripts
1. WHAT YOU WILL LEARN: Developing any project
scope requests that you identify the requirements
for the product, service, or even
results of our project and all the work required to complete a project successful. Which is something you're
going to learn how to do in this course. There are three parts to
developing a project scope. All of which you're
going to learn, okay, So these are the things
you're going to learn as you continue with the lesson. So the three paths or the
planning phase in which you put together a team and figure
things out with glucagon, put together teams that
you start working on, activities that are going
to do the prediction, number to predict and production requirements
where you collect all the necessary data and
authorization for the project. And finally, writing
a project scope, which is where you make your
project scope or fissure, all of which are covered here. Now here's the thing,
but the time you're done with this, okay, but
the end of this course, you're going to be
in a position to actually not only
learn all that stuff, but write a project scope. So you are going to assume
that we want to do undertake a porous structure and
you're going to have direct the project scope
for that construction. That is going to be part of our project, the course project. Because the whole idea here is learning by doing
our muscles manner. That teacher right
here on Skillshare. And I focus on things
relating to business, finance and legal aspects. So as you're going
through these, you happen to have a question. Don't just sit there, don't
hesitate to ask, right? Because that is how we learn. So let's get started.
2. ASSEMBLING THE TEAM AND KICKING THINGS OFF: Predict cycle can be
summed up as follows. Initiation, planning,
execution, monitoring, and control, and finally, closing in project management. Once you've secured
the agreement of the relevant stakeholders, which is something you
normally do by giving them the project charter and
having them committed to eat the planning phase stats. Usually this involves
assembling a project team. You need to bring together the people are
going to work with. And that process will mean
getting into details. Getting the details
regarding things like the work required to deliver
the project objectives, the requirements
and deliverables as promised in the
project charter. The project manager
in this case, you have to ensure that
the team you've selected, the team you've put together
has the required skills, the necessary skills needed
to achieve the requirements. Because if you put people together because
they're your friends or relatives and they can't actually get the
project done, then. Well, there are a lot of things that are
going to go wrong. The entire project team may not be engaged in the
planning effort. However, the key or most critical team members must be engaged in the planning. Once you bring
together the team, their normal at this point, you have the kickoff meeting, okay? Which is, which is a good
way to start start with an official meeting that shows that things are
now checking off. The purpose of this
meeting is to bring the team together to review
the project charter, to ensure that everyone understands why the project
has been initiated. And to ensure everyone knows what the project
intends to deliver. This actually becomes
a good way of also engaging your stakeholders
or the project sponsor. You, during the kickoff meeting. You also may want them to
be there so that they can see that things are moving
on in the right direction. So that is the first part. Okay. So you remember you had a project charter
and these people have a grid tweet and now you're
kicking off your project.
3. WHY WE START WITH SCOPE OF WORK: If you're going to have
any decent predict plan, then you obviously need
to start by clearly defining the scope of work
to be to be undertaken. Projects scope
defines the project in terms of what
will be produced. These are the deliverables
and all the work required in order to produce
the project deliverable. So there is my, we start
with the project scope is, okay, just think of the
project, the triple constraint. Okay? The projects
triple constraint are talking about the scope, the project cost, and
the project's time. The scope of work becomes the basis for the
budget we will require, as well as the schedule
of activities. So you're not going
to know how much the project is going to
score, is going to cost. Us aren't going to know how long the project
is going to take. If you have no clue what is going to be done
in that project, instead of just goes
that way, okay, So you have to figure out
what is going to be done. Now, once you know what
is going to be done, then you know how much
it is going to be done, it's going to cost,
and how much time, how long it's going to take. Because there is a correlation
between the amount of time taken to achieve
these activities. Are there to turn a
tech and activities and how much it actually cost. When sometimes that
relationship is direct, the more time you check, the more money you spend because of things like fixed costs, branch, salary for the people or things like insurance,
all that stuff. Of course, there are things that vary, like raw materials, which will depend on the
level of production, but that isn't the
point of this video. So that is one of the
reasons why actually that is a key reason why we start
with the project scope. By starting with
the scope of work, we can build the details
of the project by establishing these
forecasts one result early in the planning phase. This keeps the project, team and stakeholders focused on the objective and achieving
the results of the project. So that will also
ensure that the team keeps the discussion
around the project scope. The scope must be defined
in such a way that all project objectives and
requirements can be met. It includes the work
necessary to monitor the project as well as delivered the result
of the project. The point is, we
need to understand exactly what it is that
we are going to deliver. Meaning what, Meaning? What is the product, service, or result
that will be created? And what requirements
must the product, the service, or
the result, meat. That is the reason why we create the requirements
documentation, the scope of work, as well
as work breakdown structure. This point, remember,
as you're going along, if you have any
question, just ask. Okay. See you in the next video.
4. REGARDING COLLECTING REQUIREMENTS: It kind of is obvious
that are not going to effectively understand
the scope of work. If you don't understand what exactly it is that needs to
be delivered in the project. Not just the final
end deliverable, but also any incremental and ciliary
deliverables as well. This will also include
the sort of deliverables required to get
the project done. So you're talking about
things like elements of the project plan and that collect the
project requirements. Input is going to
be needed, okay? It's going to be required from all the stakeholders
in the project. Your project is only, only
going to be sustainable if all the people that are
part of it are involved. Hello Somebody just going
to say I wasn't part of that and therefore I don't like it and things
of that nature. So to collect all
the requirements, you need to collect information from all the relevant
stakeholders. This includes the
project team as well. The comments for the project
and its resulting product or service can be collected by meeting one-on-one
with each stakeholder. Or stakeholders can be
brought together for a group session of
documenting requirements. And that is not just about requirements because
it also, I mean, if you take something
like bring them together, the stakeholders as a group,
successfully do that. It means that any
conflicting issues, any conflict that might, these stakeholders may
actually have these. We'll give them a
good opportunity to resolve such
conflicts because if the sponsor doesn't really agree with one of the sponsors doesn't
agree with the other, then this becomes a chance
for them to hash out. The conflict that the
project can successfully. The coef requirements
collected must support the objective
of the project. For example, if the
project purpose is to plan and implement an India party which also aims to generate future
sales for a business, then a requirement to invent non potential clients would contradict the project
purpose and objective. Also, the project one
is you have to be cautious because sometimes when you call people
for this meeting, they start generating
requirements that are not even going to
be related to the project. So you want to keep
things realistic. If you realize that
somebody's tearing away from the intended goal, then it's your job. That's the reason why
you're a manager. You're not just a
project manager. You are a manager. So the
managerial skills kickin, you have to bring them back to whatever is relevant
to this project. Remember, requirements
define what is needed in order to meet the
project objectives. They do not know
the requirements. They do not define how their
work is going to be done. So always remember that they
tell us what is needed, not how those whatever is needed is going to be achieved
or is going to be done, your comments will
generally fall in the following categories. Product, technical or
functional requirements. Project process or
management requirements, quality or performance
requirements, business or organizational
requirements, support or operational
requirements, profitability, or sales and
marketing requirements. Those are some of the things
that are going to be, to be figuring out, okay? Yeah, it's sort of need to
know these things before you just jump in and
start typing the scope. What exactly you're typing, you don't even know what
is, what is needed. So that's new collecting data
regarding the requirements.
5. HOW TO PRIORITIZE REQUIREMENTS: So before we look at
examples of requirements, I just want you to remember that after collecting requirements, okay, because it's not
going to be one thing. You are going to
have to prioritize these requirements because
it kinda makes sense that if you have a lot of things that are supposed
to be achieved, you sort of need to know which one is supposed
to be achieved fast. Which one takes priority over which one in
case the clash. So that is the reason
why you need to understand how to
prioritize requirements. A technique to prioritize
requirement is called the Moscow method or the
Moscow analysis, which means that
each requirement is going to be prioritized in terms of must-have, should have, could have, or want of
must-have requirements are critical and must be included in the project in order to
meet the objectives. Should have requirements
are important and should be included in the project if the time
and budget allows. Otherwise, they can be
delivered letter or perhaps in the next
release of the product. If, if, if you're dealing, you're dealing with a project, if you're dealing
with a product, that is basically if the
project is supposed to, to result in the development
of a given product, could have requirements are nice to have if they
can be included, but the project can still be
delivered and conceal meet project objectives without
these requirements, included, won't have requirements
and agreed to by stakeholders from
the outset that they will not be included
in the product or in the project
delivery at this time, but can be revisited in future. Again, there isn't
no you prioritize this requirement is that
this will allow you, the project manager
and the project team understand what
exactly is supposed to take precedents
or what exactly supposed to take priority
over, Overwatch. Okay? So that is, that is
why this is important. The privatization is important, not just something you do
because it's something you supposed to do as
you're managing projects, we just put a tick. It is important by
prioritizing requirements. We these parity levels. This allows the project
manager some flexibility when building the project
budget and schedule. For example, if all
the requirements are to be included in the scope of work and the budget is not sufficient to
deliver them all, then the project
manager can remove some of the could have or should have requirements from
the scope without jeopardizing the project
purpose and objectives. Of course, it just don't
remove these things because you aren't going to
remove something. Or when you've
removed something, you will let the
stakeholders know that something has
been checked out. Because somebody might be very powerful that in as much as those things were could have. I'm really hoping to have them when they've been taken
out of the project. You let them know at all
times the project manager must ensure that the
requirements traceability matrix is kept current to indicate which requirements
are included in the scope and which are not. So that is the reason
why you need to have the traceability
matrix door. That is something that you're
going to look at in these, as we continue as well.
Support that beat. If there is any question
as always, let me know. And that is how
you approached it. That is how you prioritize
the requirements. Okay. So see you in the next video.
6. HOW TO DOCUMENT REQUIREMENTS (Requirements Traceability Matrix): Here's what we know so far. All project requirements are
collected and documented, reviewed, and approved
by stakeholders. The requirements
become the basis upon which the work
activities okay. First of all, the scope of work, those requirements
become the basis upon which the scope of work is defined and activities to be
undertaken sort of created. This is where requirement
disability matrix comes in. There is a multi matrix
is a grid that links the product requirements from their origin to the deliverable
that satisfies them. Recommend traceability
matrix provides a means to document
each requirement, as well as which objective and deliverable it is
associated with. It also provides the
means to document the agreed to priority
for each requirement. So we're talking
about a simple table that will show how a requirement can be dressed from the source all the way to the execution
phase of the project. So if we are making something, we are making, the project is about making a simple gadget. Then why is it circular? So something like that
can be traced from wherever suggested that all
the way to the final result. So that is what the
traceability matrix does. Here's an example of such. In this case we have
a separate networks and the party that
is the whole idea, these requirements
traceability matrix. And let's say I'm
the Project One is the right, is what we have. We have the traceability
matrix has categories, which the functional categories, the number of
recombinants we have, and then the priorities
and objectives. What are the objectives
regarding the requirements? The deliverable test, and whether it was the delivered,
whether it is accepted. So like in this case, we have the first category, F1, okay, So you've written them
as F1 all the way to the numbering system
kind of just varies. These are functional categories which have to do with the activities
that you're creating. And then we have project categories which are basically related to
the project itself. Okay? So let's see, for example, the faster the
party must be able, the party, the
party space must be able to accommodate 200 guests. We've tables and
chairs for eating. And then the space. What about the space? The space for all the 200 degress should be 250 square feet
area and all that. So this is something
that we must have. Why? Because the objective
here is to have our guest remain seated
for at least two hours. And now we know that this
one has been achieved. Well, it will depend on the
setup and how do we check. So we'll check the size, the number of tables, as well as the number of chairs. And was this something
that was approved by the sponsor? Yes, it was. And so that's something
that must be held. What about something
that we should have? Something like the participants requires a list of
confirmed guests, names that will be attending, at least in this case, seven days in advance. So it is something
that we should have. Of course, the objective
is the same to have the guests suited for
two hours and all that. How do you know that this
one as well? It's simple. We will look at the guests. And what exactly do we
look at from the guest? Those who have RSVP as
per the required debt. So look, these are things
that those are things that, that is an example of, that is an example of a
traceability matrix. One more thing, if
you look at this from the project point of view, Let's say something that okay, so must have, must
have been predicts. An example, your project
stakeholders requirements will be documented, tract,
delivered, specified. Notice that is something
that we must have objective. We need to have at least
two interfaith guests, comments and all that. So, um, yeah, that is an example of the
predictors ability matrix. And do your budget. I mean, I don't want to go
through the entire thing because I've linked it in the resource aspect of these, of these lessons so
you can download it, go through each, check if there is something that is not clear, ask I mean, it just don't
want to waste your time by reading each
box and all that. That is an example of a
project's traceability matrix. You need to have that because, I mean, not project
requirements, sorry, because you can trace the requirements
from the origin. You can just check,
was this on achieved? Was this an achieved was
not dishonest, not why? Because it failed at this point. That is what that does. So project management can be as simple and it
can be as complex, but the basics are
still the same. If there is any question
as always, let me know. See you in the next video.
7. WHAT IS A PROJECT SCOPE: If a project is a
ventrally a grid, the contractor or the project
manager will have to ensure that the customer's
specification is satisfied. In every respect. The project manager's
commitment will not be confined to the
technical details, but must also encompass the fulfillment of all
specified commercial condition. That is where the project
scope statement comes in. Of course, the question is, what is a project
scope statement? Now, these are key document to define the scope
of the project. The project scope
statement is similar to the project data in that it defines the objectives and deliverable for the project. However, the scope statement is prepared during the
planning phase and as such, will be more detailed
than the project charter. Let's say you have no clue or a project charter
is actually it's, it's, it's something that once you're done with this
course, you can just check. It's also one of the
causes that reading is or the predicts chatter compares
with the project scope. So the predict shadow
will show the following. The project Papas, measurable project
objectives and related success criteria,
High-level requirements, high level production
description, boundaries and key deliverable
overhead project risk, summary, milestones schedule, pre-approved
financial resources. Key stakeholders list in our predict approval
requirements. Project exit
criteria, assignment, assigned project manager and the responsibility and
the authority level, name and authority
of the sponsor, or even other persons
authorizing the project charter? Yeah. It looks like if it
has many things, but those things are
not as detailed as what you'll find in the
project scope statement. The project scope statement
will show the following, but in a detailed manner. So it will have project's scope description
that is well elaborated. Project deliverable, the acceptance criteria,
and project exclusion. So what I'm trying to say
here is that you see, you develop a project charter with one thing in mind to show the relevant stakeholder or stakeholders what the project
is going to be like, Okay? So that they can
accept the project, so that they can
approve the project. Once the project
has been approved. This chapter is kind
of just designed to secure their commitment. Once that has been secured. Now you stop there, we'll walk, you tell them what
is going to be done there you come up
with a project scope, which is now a more
detailed version of what is actually going
to be done in that project. So project charter intends to secure the agreement of
the project stakeholders. The project's scope is
supposed to show them what exactly is going to be done or is going to
happen in that project.
8. PROJECT SCOPE DESCRIPTION: In this section of the project, you are going to give a narrative description
of the project. And the expected results, of course, are going to be more. We're going to give more details because these different
from what you wrote in the project charter
in the sense that in the project charter you
just reacting that with an aim of securing the agreement of this
relevant stakeholders. Now that you have the
agreement and commitment, it's time for you to
give more details. The project objectives are also indicated which bidder must
be clear and measurable. Okay, let's, let's look
at that in practice. Alright, so you
have your project description in this case. First of all, the
project project is the desert networks
and the Apache. And yep, So what exactly
is this predictable about? That is shown in the
project description. But the purpose of this
project is to plan, is to plan, implement, and evaluate their IP network or the end of your party
for 200 friends, business, or even colleagues and neighbors in this case.
Why are we doing that? Because you want to thank
them for their support and business and
friendship over the years. Now, how does that help us
from a business point of view? Well, we're thanking them, as well as to generate
new sales opportunities. So this is important
for our business. Now the project must meet
the following objectives. One, to ensure our guests feel valued and enjoy their
food and entertainment. Which will result to the wrist, which will result into the
guests remaining seated for at least look at supposed to be at
least two hours or more. Sorry. Now, the guest, number two, guest Mac, at least
25 positive comments. Okay, good the host,
that is something that will help us to figure out if they enjoyed being there or not. And you also intend to generate
at least a minimum okay. To generate a minimum of five prospective or the
prospect sales order, which include specific
follow-up appointments. So that is actually an example
of a project description. Notice it tells us what
the project is about and it tells us why exactly we are
undertaking that project. It's not just for a
social reason because in this case it's actually
a business project. The India parties,
not just a party, we are doing that because you also want to get some cells, some cells deals from it. Alright? So that is an example
of project description. If you're writing yours, now you can start doing
something like that. Okay? What is your project
description? What project you
want to undertake and put down the description.
9. ACCEPTANCE CRITERIA: This now is the pathway you write measurable criteria
that key stakeholders used to give approval for the deliverables and
objectives of the project. And that is going to look
something like this. Alright, so in this case, our acceptance criteria
would be heavier. But the word all planned
activities received on time. And we denote that delivery of material or food, provide food. Table chairs for maximum
of 200 invited guests. Um, something like the budget, the budget for the party does
not exceed $10 thousand or even ensure that less
than ten per cent of invitees, not sure. So you want to make
sure that there are no accidents or illness costs to the people who've attended. Ensure the party proceeds regardless of
weather conditions, which means you're going
to have to take that into account that the
weather can go wrong. Basically, these
are the criterias that the stakeholders
used to approve the, the undertaking of the
project and that become part of your butt of the
acceptance criteria, Which means what, which means as you're going
through the project. So that as you're
writing the project, you project you, you've
chosen to undertake, if you can, let me know that. Talk about that. The people are going to
finance this project. If it's going to be financed by other
people or the people can be affected or affect
this prediction directly. What were their, their, their demands for that project to proceed or not to proceed. That is something that
you write in these, in this part of
your project scope. Okay. See you in the next video.
10. PROJECT DELIVERABLES: Okay, So now you talk about
the outputs of the project, which is what deliverables are. Deliverable can be
those created during the planning execution or even the closing
phase of the project. In case of a party,
our end-of-year party. Here's an example of those. So we have our project
deliverables in this case. Now, look, the project plan is documented and approved
by the participants. And then we have the debt given. And the plan is
supposed to include all these components we can about the organizational chart, the scope statement, breakdown
structure, the budget, the schedule, risk plan, all this stuff are part of
that particular deliverable. We also have another
deliverable repair guest list by 15th. And that will include these going to be part of
things that you're going to download in the resource so you don't
have to read all that, but just follow along. Okay. Next, the supplier
contracts negotiated, this should have
been negotiated by should be negotiated
by fast to me. And what are the things
that you're going to be looking at as
you negotiate tech. An example of this,
a document of complete list of all suppliers
that will be required for the party and confirm with the participants
or all that stuff. We have supplier
contracts are awarded or at least approved before
they're already that are approved by that debt. Supplier. Deposits of page
invitations are mailed. All these are going
to be part of the things that amount
to deliverables. And that is something that
you need to make sure that is there as part
of your project. Now, you will notice that there are a lot of deliverables because if you're going
to undertake the project, pay 10 thousand for the project, then the question
is, where we'd bring the project because you
want something, okay? Remember that triple constraint, that is the project scope, which is exactly that's
project's going to do. There is a term,
there is the budget. Sometimes the scope can also
be called the quality, okay? So the thing we intend to achieve that is important and that is what
deliverables are. Therefore, you really
have to be serious about this bit of
your project scope. Just contract for
things and then say, yep, I'm done, move on. No. This is what the
project is all about. So ensure that you've given it your all and you've
you've written, you've routed
properly, basically. Again, if you're struggling with anything at this
point, the lamina. And remember, again, you can
download the PDF version of this in the resource
bit of these costs. And then you can use it
as we, as we go along.
11. PROJECT EXCLUSIONS: This bit is very
important in your project because the client could
just want anything, glands, plants want many
things in that project. But then it's
important for you to let them know that there are things which will not be in
this particular project, even if they are normally
there in other projects. And that is important, basically the project exclusion, that is what we need
to talk about, which, which could include features, functions, service,
or deliverables. You let them know that those
features, those functions, those services, are not going
to be part of this project. So you let them know that
in the project scope. Um, here's how you do that. Alright, so in this case, we let them know that no
additional insurance needed. Now, additional
insurance need to be procured in order
to hold this party. That is something
they need to know. A photographer will not
be included in the scope. So if you're under photographer, get your own or
pay extra for one. No floral arrangement will
be included in our party. Party. We don't really want to worry about
the floor arrangement. And that is those three things are things that they should
not expecting this party. So it depends. It could be a website because somebody
has you to build them, a website or somebody has you to build them are softer and
then they start saying, my friend has this website
and it has this thing. Will that also be here
and then tell them no, that will cost you extra. Or there's this
software which does a, B, C, D, will mine also do that. It's like that is the reason why you have the exclusion
bit so that they know that these are
not going to be yes, they are normally there
in similar projects, but they're not going
to be there in diesel. And the reasons are 123. Right? So that's the thing.
12. CHANGE MANAGEMENT PLAN AND CONTROL BOARD: What if a stakeholder
has something that they want changed
in the project? What if as a project manager, you want something changed? How you manage
changing the project is the main thing that you're
going to be talking about in this patch and short
change management plan is something you want to show in your project scope statement. Things that can change
the project will include the project
scope, deliverables, requirements, budget,
or even the schedule, despite the consequences
of changes. Okay. Despite the
results of the changes, all changes must be documented, tracked, reviewed, and status. Also, don't forget to show the person who's
making the change. Why? Because we need to
assign responsibility. So the person who
initiated the change or the parcel know basically the person orchestrated
the change or the person who
approved the change, we must show that person. Now how do we do that? Well, here's how we do
that in the project scope, this patch, you're talking about how change
you'd be managed. So these are going to write or something along these lines. Okay, so in this
case, we have we have the change management
plan and control board. Regarding the change
management plan, talking about change
control process, scope will be
managed, monitored, controlled by means of
work breakdown structure. Alright, created by,
created for this project. And that is just going to go into carbo to
work breakdown structure. You're talking about
hierarchical structure, which shows a task and all the activities
involved in that task. If there is any change
that is going to be reflected in the WBS, any changes required
externally initiated by a client or internally shift
where they predict team will require a change order
to be completed. Let me show how the
change order is. In this case, we're
talking about this one. So this is the
change order form. So if there is any change
that is to be made here, it will be reflected here. So we have the project name
and then there is the debt. And we have the project manager know who's requesting
for that change. Then we have the
details description of the proposed change. Why the reason for that change? How will that change
impact on the project? And now that they've
written that, well, then you also show to be completed by the
change control board. These are the people
these were it will show whether the change
has been approved or not. So we have these analysis
required and all that stuff. We have the change thetas
as it had been approved, as it had been rejected, as it had been deferred. See, all this stuff. Alright. All these is just part of the part of the change order which is required to
be to be completed. Now the change
board itself. Okay. These are the pupil are
going to be to be in charge of the change and
what these people. So you show, in
this case we have the project manager,
the sponsor. Because remember,
our US is a party and external stakeholders
such as supply, because sometimes the change
you're trying to initiate, you don't want one supplier
or something blue the supplier they
supplied certain type of food you do answer that. You want that change
to your like nano we're honored percent vigor. So something like that. And then you want
that to be changed. So how will that affect the
project's scope or elite afraid the project time? How will it affect
the project cost? So that's why the
external supplier has to also be involved if that
change relates to them, okay? So that is how you manage
change in the project.
13. HERE IS YOUR ASSIGNMENT: Okay, so now at this stage,
I just want you to remember that the idea here is
learning by doing. And so as you go through
that onto to assume that you are about to build
a house or your project. The project in this case, honored to assume
that you're a project manager and the project
is building a house. Don't worry. If you don't know anything about construction
that is not important. The important thing is
you make up the details. I want you to write a project
scope statement for that. Okay? It's part of it's
part of your project. So don't worry about
being wronged or a boat, you know, all that. If you are stuck at any
point, do let me know. So write that.
14. NOW THAT YOU ARE DONE: Now that you're done
with the course, I mean, it's not really
that long of a cost rate. Just want to point out that if as you're going through this, you find it helpful, don't hesitate to give
it a positive review because those are important
for a number of reasons. One, it helps other people to also be in a position to access
this course because it's, it's, it's recommended to them. And also tells me to know if this course was
helpful to you. And of course, if there
is any question has evolved as pointed out
throughout the entire video, you ask and also, and to recommend another
course which I did on outright our project charter
and manage stakeholders. So that is something
that you can also check in after you're done with this or know that you're
done with this one. Because a project charter comes first and then the
project scope statement. So you can check the tone
that OneNote as well. So I'll see you in
the next course.