Transcripts
1. Course Introduction: Are you writing a
project charter and are finding it difficult to
document the stakeholder list? Project risks and assumptions. Do you need specific
guidance on what should and should not be included in your
project approval. Include your requirements. Do you want to understand
what the sponsor needs during the
project sign off stage. If your answer is yes
to these questions, you have come to
the right, please. As a project manager, you will always
document and create a project charter as the
first step of any project. A typical project charter
includes all these components. In this course, you will
learn these components of a project charter,
stakeholder list, project risks and assumptions,
project approval, enclosure requirements, and project sponsors
and their sign offs. Documenting your
stakeholder list includes appropriate
identification of stakeholders, project risks and assumptions. Have a word, any potential issues that the
project may face. Project approval
enclosure requirements are basically those
actions that must be completed before the sponsors signs off and fully
approves the project. These components of your
project charter are read by the sponsor and
project of LOINC committee. And based on what
you have documented, they will either approve
or reject your project. Now, I have seen several
projects being rejected because either the stakeholders were not identified accurately, risks and assumptions were not forecasted as they
should have been. Or approval enclosure
requirements were not met. These components of the
project charter were documented by some of the
seasoned project managers. Yet, the field, the reason
for their failure is simple. There project stakeholder list, the risks and assumptions and project approval and
closure requirements were not thought through. They were incomplete. The project managers did
not pay much attention explaining and convincing
their approvers that their project was critical. As a result, their documentation
failed to impress. If you want your project
charters to look comprehensive. If you want your project
stakeholder list, risks and assumptions and project approval
enclosure requirements to provide a complete picture. If you want these components to trigger an immediate action from the senior management to approve your project, funded
and promoted. You must do this course. I have executed several 100
projects in the industry, and each of my project charters
were instantly approved, funded, and promoted by
the senior management. And I'm happy to share
my knowledge and expertise to you
by virtue of the streaming with that background
information of what you will learn in this course
and why it is important. We will start our
learning journey.
2. Document Stakeholder List: Stakeholder list. Stakeholders are
vital constitutes of your project's
success or failure. Stakeholders are those who will get impacted
by your project. You must include the names of all those who fit this category. Stakeholders also include
those who impact your project. You must include their names to. Identification of stakeholders
is an ongoing process. You will continue to update the stakeholder list as
the project progresses. At this point in creating
the project charter, you must update all the
known stakeholders to date.
3. Document Project Risks: Project risks. Project risks, if not handled well, can throw your project
of the course. In this lecture, you will learn what our project risks and how to identify and document them in your
project charter. Let's begin. What are project risks? Project brings about
the necessary change in any business process. When any change gets introduced, it brings with it several risks. These risks are
potential situations that may occur in your
business process. There are two major
types of project risks. Positive risk and negative risk. Positive risks are enhancers. They bring about the
necessary improvement and enrichment in the
outcome of your project. These are value enablers. For example, your project team might create a byproduct that may result in huge revenue and profits for the
business process. Negative risks are
potential failure modes. They may cause your
process to break down or could throw your
project off completely. There are more chances
that your project may come across negative risks, and hence, you must be prepared to tackle them as they arrive. No two projects may
have the same risks. If you are not aware
of your project risks, you may allow them to occur
and impact your project. Identification of
risks is vital. How to identify
your project risks? You can identify project
risks in several ways. One of the ways is to observe the process map of
your business process. Process map is nothing
but a flow chart that depicts each step
of your business. You can conduct a
brainstorming session with the subject matter
experts, stakeholders, and your project team to review
each step in the process, map, and identify
the potential risks. Another way to identify
project risks is to observe processes in the same
or similar industries. You will get invaluable insights as you studies
similar processes. Identification of project
risks can also be executed using tools
such as brainstorming, interviews, surveys, focus
groups, among others. You can use these
tools to gather inputs from your project team, subject matter experts,
stakeholders, customers, etc.
4. Articulate Project Assumptions: Project assumptions. What our project assumptions? The project charter is created at the beginning
of the project. You will not identify all the project
requirements at this stage, nor would you have
collated enough data. Basically, you will not have all the necessary knowledge and information you really need. In this situation, you can make certain assumptions and
proceed with the project. As you move through the
project journey and gain more insights and clarity, you can alter these assumptions. For example, at the
beginning of the project, you may not know the
vendors labor rate. In this situation, you
may assume the amount of this labor rate based on a fair understanding
of the market. Once the procurement team
raises a request for proposal, you may ask them to include this question on the labor
rate in the proposal form. Until then, you can use the assumed labor rate to calculate the project's
overall budget. And you can also add a writer indicating that the sponsor may expect some variation in the final budget figures
because of this assumption. Why is it necessary to document assumptions in
the project charter? When you assume
something in a project, you must make an
effort to confirm it. In most situations and
individual or a group of project team members may assume something and the reality
may be totally different. Hence, it is necessary to
have these assumptions documented and circulated
to all stakeholders. If they have a
difference of opinion, they can voice it now and mitigate any potential
challenge in the future. For example, let's say you
assume the labor rate to be $100 per hour and factored
the amount in the budget. When the finance team sees this labor rate in
the project charter, they may advise a 15% tax
to be added to this rate, increasing the assumed
cost $215 per hour. This will be a big difference
if the project plans to hire the vendor labor
for hundreds of hours. If the project manager
fails to write this assumption in
a project charter, he or she may have
missed the gap of $15. That would have been
a colossal mistake.
5. Write Project Constraints: Project constraints. Every organization has limited time, money, and resources. Each organization operates
under some constraints. This situation also
applies to your project. Your project may be pressed
under some constraints. In this section, you must identify those constraints
and document them. Remember, you are still in the initial phase of
your project journey. It is okay to document the project constraints
at a high level. Typically, project
constraints can fall into any of the
following categories. Scope, schedule,
budget, quality, resources, risk, and
contractual related. Depending upon your project, there may be other constraints to how would you identify
the constraints. Meeting with the
project sponsor. Project sponsor is one of the most significant sources
of this information. Our project sponsor in most situations exactly
knows the constraints that your project may have a discussion with the project
team and stakeholders. Project team members and
stakeholders may add a few unknown variables that may be constraints
for your project.
6. Determine Project Approval Requirements: Project approval requirements, project approval requirements, or those requirements
that need to be fulfilled before the sponsor
signs of the project. It outlines the conditions to be met for approving the project. This section, the project
approval requirements, also articulates
the individuals who have the authority to
sign off the project. Documenting these well in advance in the project charter
has a few key benefits. It sets the expectations with the key stakeholders
that they will review and approve the project after the necessary
criteria are met. It involves the
approving authorities in the project activities
and its progress. It also creates the necessary buy-in
from the stakeholders.
7. Identify Project Closure Requirements: Project closure requirements. The project approval
requirements discuss the conditions which must be fulfilled to fully
approve the project. This section, the project
login requirements, articulates the requirements
that are to be met to close or terminate the
project or its phase. There are three
scenarios involved here. The project or a
phase is successful. The project or phase fails, or the project or phase
needs to be scrapped.
8. Sponsors and Signoffs: Project sponsors and
their sign offs. Once you have completed
the project charter, you are required to set
up a review meeting. The review meeting is presided
by the project sponsor. You would be the facilitator
of the meeting and the invited parties will include the project team members
and the stakeholders. You would have the
project charter and the supplemental documents ready for the sponsor to review. You would also need to
have the right parties invited to the project
review meeting to answer in any
potential questions or address any concerns that
the sponsor may have. Once the meeting is over, the sponsor would either reject the project or keep
the project on hold, asking for more revisions
or sign of the project. Rejecting the
project may happen, but it is rare. Keeping the project on hold. Asking for more
revisions would mean some critical aspect of the project is missed
to be included. The sponsor may also ask to send a revised project charter for approval or hold
another review meeting. Sign off the project is giving a sponsor stamp of
approval for the project. It means that your
project is now official and you can move to the
detailed planning stage.
9. Mini Project: Mini-project. Now that you are fully
aware of all the steps needed to document
the stakeholder list. Project risks, assumptions
and constraints, project approval and Clojure requirements and
projects sine ofs. Here's a mini-project that can turn your
learnings to reality. First, based on your
learnings from the scores, make a list of the do's and don'ts of documenting
the stakeholder list. Project risks,
project assumptions, constraints, approval,
include your requirements. Once your list is ready,
document these components. If you are already
working on a project, this activity can be
executed for that project. Or if you don't have a project, you may think of a
fictitious scenario and practice your
newly learned skills.
10. Course Conclusion: Course conclusion. So we have come to the
end of this course. Let's recap your learnings. You began this course journey by understanding how to document
the stakeholder list. You will learn how to
write the project risks. You then learned how to write the assumptions and
constraints of your project. Further, you learned
how to document the project approval and
closure requirements. By the end of this course, you learned what goes into seeking project
sponsors sign offs. That was your overall
course journey. We have come to the
end of this course. Please do share your review and I will see you
in the next course.