Transcripts
1. CLASS 01 - INTRODUCTION: Hi, I am Said Soliman. I'm a Projects Management consultant and acting as Managing Director
for consultancy firm called "EDGE" for
cost management. In My role, I worked
with a lot of teams, whether they are from agencies, startup companies, internal
teams, or corporations, and help them solve their
project management challenges, especially in the scope
of cost analysis or in the rule of business
process management and the ERP implementation. In our class. I will clarify the different
and the common methods of cost analysis and
what's the difference between them in terms of use, method of analysis and the amount of information
required for each method. This is to determine
the method that suites your needs according to the nature of the project and
the purpose of the study. In this class, you will
learn about is the main and the most common types
of cost estimation like Rough Order of
Magnitude method, Preliminary Estimation Method, Substantive Estimation Method, and Definitive
Estimation Method. What's the related techniques of estimation for each method? Like Analogous Technique, Parametric Technique, and
Three-Point Technique. and that to enhance your choice
for the best methods that matching your requirement to
estimate the project cost. By the end. and to make the
best out of this class, I recommend you to use one or more of the technique
from this class to put together an outline of an approach for a project
you are planning to estimate. And that by answering the following question to consider when building
your outline. What's this type of question? First, what's the purpose of
estimation for this project? How much information
is available? What's the level of accuracy
required? Thank you. And let's get started. Our first lesson.
2. WHAT ARE THE TYPES OF ESTIMATION ?: Welcome to the first class from the subject of principle of
project cost estimation. In this class, we
will talk about common types of project
cost estimates and what's their criteria which
enhance our choice for the best method is that matching our requirement to
estimate the project cost. First, we must clarify what
is meaning of cost estimate. Cost estimate, a
quantified expectation of how many resources are required
to complete a project. Such cost estimates are often expressed in currency units. However, other units
such as man-days, can also be used if the current amounts
are not applicable. or irrelevant. Now the question is, how many methods we can use to implement estimation process? Actually, there are different
types of cost estimates. And this class, we will talk in detail about the main and
most common three types of cost estimation and what is related techniques of
estimation for each method. The first one is the
approximate estimate by volume, which is called also
rough order of magnitude. This type of estimate is
used to for project screening or deciding which among several projects
to proceed with. That often based on high
level expert judgement, sometimes in conjunction with
the three-point estimating, which is one of the estimation
technique that reflect the average of optimistic, pessimistic and
most likely estimate. Second method is the
initial assessment of the main project item, which is called the
preliminary estimate and also called the
budget level estimate. And this type of estimate is used to support in
decision to choose among the various options
available or to make a decision to proceed with one alternative over the others. Accordingly, estimate
needs only to be as detailed as necessary just to compare between alternatives. The last method is the
accurate method of analyzing and
determining the price of each item of the project. and this method called
substantive estimate. This estimate breaks down a project into its
component parts and uses all
available information to assign a cost to each part. The pieces are rolled up
into an overall estimate, then contingencies and margin
and the profit are added just to in their summation to
estimate the sale price. Now to facilitate understand
of the different cases in which the previous methods of projects pricing are used. I will illustrate these
cases with an example. Suppose that a construction company nearing capacity of employees, at its
headquarter building. And I identify the need
for an expansion. And the construction
work for such expansion definitely will be executed by them as they are already
a construction company. Two years prior
to construction. An order of
magnitude estimate is developed to understand
the scale of the expenditures
that implemented based on price of previous
similar project or based on expert
judgment by considering the common price in market for the square meter
of building area, built-up area for such type
of building, which is a CEO, uses to make the decision to proceed with the construction
of new building for expansion and saves the
required budget that will be considered in the further
financial plan for the company. One year later, and as they became
closed for the execution of such expansion project team present the CEO with
several options for expansion. Even it was vertically, so additional floors
or horizontally through the construction
of adjacent new building. Based on these alternatives, the initial design and configuration assigned
for each alternative, and accordingly the
preliminary estimate for the major trades
ONLY implemented. Why the major trades? Because the initial design just give us information
about the major, information about the building. Based on these estimates. One of the expansion Design
is chosen, six months later. The chosen expansion has
been completely designed. Quantity of material are known. In this stage,
a substantive estimate implemented for each
item in detailed. Each item from the bill
of quantity sheet, which contain all
activities will be done to execute
such building. Each item in detailed is presented prior
to construction. In the next lessons
through this class, we'll clarify each method in detail separately,
respectively.
3. ROUGH ORDER OF MAGNITUDE: Now, we'll start talking about the first method of
price estimate analysis, which is called rough
order of magnitude. It's typically used in the preparation and
initiation phase of projects. For the development to
project business case, for the determination of the required financial resources that are stated in
the project charter. The rough order of
magnitude method is typically used for project in the initiation phase with a high level of confusion
and the uncertainty. With respect to the
expected cost where, the required input data for the estimation technique may not be available at the time being. In other words, the
available information is just a general idea
of the project which was put forward
by the owners. Of course, not
sufficient to obtain the exact price of the
project component. Because such
information may be in the range of 1% to 5% only. The estimate value for this
method is usually having a variance of negative
50% to positive 50%. It's to provide a
rough estimate, of the total expenses that
the owner may incur. until, the project
is completed. An estimation approach known as top-down is
mostly applied here. Whereas the overall project
either estimated first, then individual task
or allotted from it. or the project is broken down into larger tasks that are
estimated separately. However, we may need it to get approximation and the estimated in general for the
project price. And in that for the
following reasons. First, for Feasibility studies in which you may
need a total value only of the cost of establishing the project to enable the owner to make
the right decision. Second choice, we may need it in the marketing
for the project. Whereas there are some projects, especially residential
or commercial, you may need to market
them in advance. Sometimes the marketing team may request an initial price
per square meter of the project based on
which a marketing plan is drawing up and provide unit price to
customers based on it. That For what? For the speed of presence
in the real estate market to provide part of the cash needed to implement
such a project. Now the question is, how we can do it? Actually, there are many different
techniques , your team can choose. These techniques can be used individually or in
combination with each other to arrive at a
more accurate estimate. And in most cases, a project manager will need expert judgment and
engage Technical Leads. So, what are the appropriate
types of techniques could be implemented with
the rough estimation? First technique called
analogous estimation. Analogous estimation. This technique uses
data and the knowledge of previous or similar
project as the basis for estimating the new one
will be an instance where the project manager
is asked to give a duration and cost
forecasts for new project. As the owner needs some data to decide whether the
project is worth doing. In such cases, an
analogous technique is the best solution. It's often used when. Much information about the
project is not yet known. But, the accuracy of this
approach is the lowest amongst the
further techniques. However, it is the fastest and
cheapest estimate to make. Getting data on a
previous project is usually a few clicks away, especially if the project
was done by your team. This estimation technique can be applied to the project as a whole and to the individual
tasks of the project. But the pitfall of the analogous techniques
when using this method, the project manager assumed
is that all variables in the past project remained roughly the same
for the new one. However, the variable, such as cost are constantly changing, which may lead to a
significant deviation from the actual cost or
duration of the project. So, to avoid such pitfalls as
possible as we came. it is preferring to
consider a percentage of the expected
escalation of prices based on the periodical document issued by the official
organization, organization or a
governmental organization. For example. Previous similar project costs, maybe it was $15 thousand. To complete it in three months. Therefore, the new
project should cost about $20 thousand. Why, we increase the
value from 15 thousand to 20 thousand because we comparing the two project. Many different variables are taken into account
such as scope, cost, inflation,
duration, and so on. OK, The second technique
could be implemented with Rough Estimation is the
parametric technique. The parametric technique,
makes use of cost unit tree taken
from previous projects. And consider these
rates for the assumed quantities in
the new project to determine the estimated cost. For example, based on the
master plan of the new project, we can assume the approximate quantities
of the main tasks, such as the volume of concrete and the area of various
finishing works. Then an initial estimate of the unit rate price
of this item is made according to the
prevailing market price or based on previous
project data. So, we can estimate the cost
for each major task. Therefore, by rolling up
their estimated value, the whole project costs
will be estimated. Actually, the accuracy of the parametric approach is
quite more accurate than the analogous estimating because the parameter value are
taken from several sources, like industry publications or similar projects
which wide our search. and accordingly, our
estimation be more accurate, but the same is a pitfall of
the parametric techniques. The overall estimate is only as reliable as the
parametric value. So, the accuracy of the
project estimate maybe greatly skewed. If the parametric value
is very small and the number of units is
very large, or vice versa. For example, assume
that estimate "A" equals $1 per unit and the
quantity is 1 million unit. So, the total of estimate "A"
is $1 million. Second estimate "B"
the unit rate is $1000 per unit and the quantity is 1000 units. The total of estimate "B" is
$1 million is the same like estimate "A" we see that even though the estimations
are the same. A small mistake in the
parametric value of estimate "A" will cause a significant increase in the value of the
final estimate. However, that is not the case of estimate "B" because
the unit rate is $1000, so any change will not impact aggressively on the
total estimate would be. Another obvious drawback is
that a parametric estimation required a lot of historic data which
may not be available. We talked about two techniques to implement the
rough estimation. The first is analogous and the second is
parametric technique. Now, let's talk about
the third technique could be implemented with the
rough estimation, which is called a
three-point estimation. Three-point technique uses
optimistic, realistic, and pessimistic estimate to get the most accurate
value for a project. The best thing about the
three-point technique is its ability to accommodate for the uncertainty
in project time. It also makes use of
many of factors that can delay or accelerate the
project's progress, Actually, by using the
three-point technique, project manager can have an idea of the
possible costs and the time variation for
the deliveries and offer delivery dates to the stakeholder in
a safer manner. What are the meaning
of three-point, optimistic, realistic,
and pessimistic. Optimistic. Assuming that low-risk use. Pessimistic, is assuming that
the risks certainly accure. The most likely, is assuming the most realistic
risk occurrence level, which already is
the normal case. and to calculate the 3 estimate values. There are two accepted formula. First formula is the
triangle distribution. It's simply the average
of the three values commonly used in small,
repetitive projects. In this case, estimated costs equals optimistic plus
most likely plus pessimistic. The total divided by 3. Second formula is
BETA distribution. This formula is
also known as PERT, Program Evaluation
and Review Technique. Which takes, the weighted
average of the three values. So it's also known as a
weighted average because the most likely value has four times more weight
than the other two values. This technique is mostly used for large,
non-repetitive project. and the estimated in
this case equals the optimistic plus four times most likely plus pessimistic, the total divided by six. For example. Based on previous project, we understand that
the time it takes to design the building under the best
condition is 50 days. We then estimate the
time it will take. If the worst-case
scenario cues such as the expected missing of
information or things like that. Let's say it's around 150 days. Then we assume that
realistic time it will take to complete that
task is 100 days. If some favorable and
unfavorable scenarios is accused. So, the estimated time to
design the building according to the three-point
estimation technique. And based on BETA
distribution formula will be expected time equals 50 days, which is an optimistic plus 4 multiplied by 100. 100 is the most likely
plus 150 days, which represents the
pessimistic expectation, the total divided by
six equals 100 days. So the expected time for
this task is 100 days. The pitfall of the
three-point technique. This method will provide
inaccurate estimates if there are inaccurate or incorrect assumption
is scenarios. Also, it will be confusing and
time-consuming if the optimistic, most likely
and pessimistic values are defined by different people. So it should be decided by the same person to be involved in the all
environment regarding this task. Now, and as a conclusion, the rough estimation method
doesn't give much accuracy, but it's considered
sufficient at this stage as it provides at
least a rough idea of the cost range of project, which is often useful
for the purpose of stakeholder communications
in an early stage. And can also
be used to develop a budget business case
or a project charter. And, the common techniques
followed to implement such method are
analogous technique, parametric technique, and three-point
technique. And definitely. These techniques can be used individually or in combination with each other to arrive at
a more accurate estimation.
4. PRILIMINARY ESTIMATION METHOD: The second method of studying project price estimate is called the preliminary
estimation, also called the budget
level estimate. This type of estimate
is used to aid in decision to choose among the
various options available. Options for the final product. Its features and configurations are analyzed and
the estimated to make a decision to proceed with one
alternatives, over the others. Hence, the estimate needs
only to be as detailed as necessary to distinguish
between alternatives. This method is applicable when the project definition
level is about 10 to 40%, which is considered
sufficient to determine the type of
main item in the project. This information is almost obtained through
schematic design, in which it becomes clear, the shape of the
general building, and the nature of material
used in construction, which has freed us with
the necessary information. Like the type of skeleton
and if it concrete material or metal structure or
something else, it provide also the number of floors and the built-up
area for each one. the different types of
finishing work. And the types of electromechanical
system will be used. Based on such information, we begin to analyze
each main item separately. Definitely, we can follow the parametric technique
in our analysis for the preliminary
estimation by counting the approximate quantities from the available initial
design drawings and then determining the expected cost for
each main item depending on the prevailing prices in the market or previous project. Additionally, we can
improve the accuracy of our results by using a
three-point technique in combination with the
parametric technique to accommodate for
the uncertainty in Project times accordingly and in submission of the estimated
value for the major items, we can get the total
cost of the project. The difference between
this method compared to the rough method noted
in terms of relatively increase the accuracy
in calculating the total cost of the project as it was relied on evaluating the cost of the mian
items separately. And therefore, the error rate in estimating the
price will be much less due to the
limited search space compared to the rough method. In addition, in this method, we have separate initial
prices for each main item, which facilitates the process of comparing the different
alternatives. how that come ?. Actually, this
method is used by the owner in the event that he wanted to obtain
several alternatives to the method of
implementing the project. Where the alternatives
are multiple, especially in the infrastructure
and roads projects in which changing the path
of Road works or method of excavation work
for mechanical pipes underground may have
a significant impact on the differences
in project value. Therefore, it's
better to analyze the main task only to clarify the difference in cost
and in which main task specifically to facilitate decision-making regarding
suitable alternative. Finally, based on the
methodology of this method is the expected error rate
in the study ranging from minus 10% to positive 25%. And it's clear that the
positive percentage is greater, in which we always assume
the quantities for the higher value is a factor of safety in our cost estimation.
5. SUBSTANTIVE ESTIMATION METHOD: The third method to estimate the project price is
the exact method, which is called also
Substantive Method. In this way, all project
information became available. And this information
is represented in full design drawings, technical specification
and the contractual terms. Before describing the process of the substantive method
or the detailed cost estimation for project. It wise to take a look at
the various cost categories associated with the project and its relation to the bid price. This figure shows the main
components of a bid price, which is being direct costs. Indirect costs, and markup. In substantive method, we will analyze and estimate the
cost of each component, which in total produce
the contract sale price. Actually several
classifications of cost are in common usage, like fixed, variable
and semi-variable is a basic economic
classification. But in the context of the
construction industry, the classification of
costs are direct cost and indirect cost is more
widely used and understood. Indeed, it's upon
such a classification. Most tenders are
prepared by contractors. How we can do it? First, let's talk
about direct costs. Direct Costs are the costs attributed to the production
of activities of a project, which represent about
60% from the sell price. They are estimated based on detailed analysis
of the resources, productivity data
and the method of construction being used
for every activity. The direct costs are
the summation of the cost of the
labor, equipment, crews, materials
and subcontractors used in all the activities in our project. By determining the required quantity of each cost element that
required to implement it, this item or this activity. And that based on the
available information through design drawings and the
technical specification for the implementation
of such item. Then, the price of each cost element is
determined according to a quotation from sources of supply or implementation
of cost element. And these sources may be suppliers of the material used or
from subcontractors. Second component,
is the indirect cost. Actually, this costs are
consisted of two categories, project overheads and
general overhead. Project overhead,
which represent about 25% of bid sell price. This include a cost of items which cannot be
directly charged. to specific work's element. This
includes the cost of utilities, permits, supervision, and so on. Which service many elements in the projects work
breakdown structure. The general overhead
which represent about 5% of bid sell price. These are costs that cannot
be directly attributed to a single project
and include items such a head office expenses, taxes, and so on. The current project’s share. Of these costs
can be estimated to be proportional to
the project value as compared to the
total yearly volume of the contractors organization. Finally, the markup. This bid components
represent the contractors the added fees as a percentage of direct
plus indirect costs. That covers two aspects. First, the profit, that depending on the
business objectives, of the contractor
organization, this item can be decided based
on the level of computation and the
contractual or contractor needs for winning this
particular project. The second, for the
Risk of contingency, which is used to provide
safeguard against uncertain circumstance that are anticipated to
affect the project, such as weather, labor problems, soil conditions, any changes. and so on. And the percentage
of markup, it's around 5% from
the sell price. Now, after we clarified the
three method of estimation, rough order of magnitude a preliminary estimate
and substantive estimate. It's worth noting that
there is another method, but it's not commonly used, is called the definitive method. In this method, the
contractor tries to avoid completely
the error rate in pricing by concluding prior contracts with subcontractors
to implement the work in full So, that all the responsibilities
and obligations of the main contract are transferred
to the subcontractors, thus avoiding any risk from the possibility
of changing prices. Since in this case, the value of the
project cost will be fixed and known before
starting the project and the equal to the value of the previous concluded contract, contracts of subcontractors. But, definitely in this case
is the main contractor. We lose part of his plan profit, which will be
transferred directly to the subcontractors
carrying out the project. Therefore, this method
is used only in special cases in which
the probability of price change may be large or the main objective
obtaining this project is to increase the volume of business for the main
contractor and not to profit. Thank you, and hope
to see you soon in my next class about
the tender document. see you later